loading
Contracts

project:-construction of 2 emergency railway bridges on raft/well foundations i.e., B.NO.5A near nidadavole and B.NO.180 near BHIMAVARAM IN S.C.Railway

Client:-South Central Railway NO.19/DEN/SW/BZA/86,NO.20/DEN/SW/BZA/86

Remarks:-Both are constructed as emergency restoration works completed well ahead of schedule.
project:-Design and construction of railway bridge no.86 with 6m well foundations near Nadikudi as 4*20.0m soans withPSC super structure,Earthwork in approcahes and protective work.

Client:-South Central Railway NO.64/CE/C/SC/1986 DT-4-12-86
project:-Construction of Road Over Bridge across Gudivada Railway station yard on Well Foundation with RCC piers and PSC decking with spans of 2*25.5m(Skew) and 1*30.0m(Skew) on a sharp curvature.

Client:-South Central Railway NO.38/CE/C/SC/1986 DT-2-9-1986
project:-Construction of Road Over Bridge with 3*14.50m(Skew) spans between Kolanukonda and krishna canal section.

Client:-South Central Railway NO.33/CE/C/SC/1986 DT-22-7-1986
project:-Design and Construction of railway Bridge No.442 with 4.50m dia Well Foundation and PSC Decking near Nashkal as 4*12.20M Spans.

Client:-South Central Railway NO.4/CE/C/SC/1985 DT-26-2-86

Remarks:-Work was completed 7 months ahead of schedule.
project:-Design and Construction of railway Bridge No.269 with 6m dia Well Foundation and PSC Decking of 6*18.30m spans in the doubling between Balharshah and kazipet station.

Client:-South Central Railway NO.45/CE/C/SC/1985 DT-28-2-85
project:-Design and construction of Railway bridge NO.93 and 42 with open and 6.0m on dia well Foundation in the BG line from Moutari to Jaggayyapet as 3 * 20.0 m spans PSC Superstructures.

Client:-South Central Railway NO.48/CE/C/SC/1985/ DT-13-3-85
project:-Design and construction of Railway bridge NO.50 across Munneru river in the BG link from Moutari to Jaggayyapet on 6.0 m dia well Foundation and with PSC Decking of 33 * 20.0m clear spans.

Client:-South Central Railway no.31/CE/C/SC/1983 DT-19-9-83

Remark:- First Longest PSC Bridge in south central railway completed 11 month ahead of schedule.
project:-Construction of emergency Bridge no 223 on Board pile foundations with 3*18.30 m girders for 3 tracks near jaipur station.

Client:-Western railway no.CE/81/BRIDGES/7/ DT-26-12-81
project:-Construction of emergency Bridge no.198 with 10*60 feet girders on well foundation Between jaipur and kanauta station.

Client:-Western Railway NO.CE/81/BRIDGE/6/ DT-1-12-81